The FAA has 11,389 separate project schedules covering 13 air traffic modernization programs. GAO found they aren’t integrated. One example: technicians are scheduled to prepare a St. Louis control center for a new voice switch in April 2027. Another crew is scheduled to return to the same facility in January 2028 to prepare for new information displays. Two separate visits for work that could have been coordinated.
The FAA is testing an AI tool to find scheduling conflicts, but hasn’t settled the rules for using it or set a date for implementation. Nine of the 13 programs already have work underway without an integrated schedule.
The money is no clearer. The FAA’s $10.6 billion Phase 1 estimate leaves out government costs and most future operating expenses. Phase 2 is expected to cost another $10.2 billion, but has no start or finish date.
Now Sean Duffy wants $50 billion after Friday’s nationwide shutdown. Congress already approved $12.5 billion for the overhaul. GAO says the FAA still can’t produce a reliable total cost or coordinated schedule.
https://files.gao.gov/reports/GAO-26-107992/index.html